Building the Subfloor for the master bedroom loft space was a big challenge and took a lot of time. Lots of activity in this video as I install 2" x 10" x 16 foot floor joists, nail up a bunch of joist hangers connected to the end beam, and glue and screw 23/32 inch tongue and groove OSB Subfloor. Most of the joists had to be notched over the Wet Wall since the concrete floor below was not perfectly flat and therefore the hump in the middle cause the wall to be too high for level. Glad to get this done and can move on to the next project